.Plan assignments with foresight! v1.9.2
Plan project assignments ahead with foresight even if you don't have estimates:
(Click to enlarge) | Let's now do the planning for all relevant resources and specific teams. Go to the Assignment Board. 1: Here you can find the filter that you previously created. 2: Create filters for all resources and specific teams as learned before. Keep in mind that you need to create an assignment first to see a project or resource in the filter selection boxes. Learn more about creating filters for projects and resources. |
(Click to enlarge) | Define a project assignment with "Distribute value in period" strategy. 1: An example: Tina Test works 50% (20 hours per week, 4 hours each day), in CW 24 she is on vacation. We want to distribute 56 hours work for her over the next 5 weeks. 2: Select 'Create assignment'. |
(Click to enlarge) | 1: Select the schema 'Distribute value in period', the algorithm will distribute the 108 hours according to her availability in this timeframe. Distribution Scheme Learn more about distribution strategy. 2: Select a project and the relevant resource (Tina Test in our example). 3: Select time frame 4: Check availability. In our example Tina has a capacity of 200 hours (10 weeks of 20 hours). Considering her planned absence times the availability is 132 hours:
4: Select the available capacity - 108 available hours in our example. 5: Save and review the result. |
(Click to enlarge) | Tina is now assigned according to her availability in the given time frame |