Ensure continuous feedback!
Ensure continuous feedback regarding planned vs. actual work. Check budget consumption of projects.
(Click to enlarge) | Check if your team(s) worked as planned. Check budget consumption of assigned projects per week. Discuss with your team(s) if planned differs from actual work. 1: Go to the Assignment Board - switch to Analytics. 2: Toggle between Projects > Resources and Resources > Projects view. 3+4: Identify projects which have negative / positive diff(erence) values. In our example the team worked 8 hours over plan (3) and the week after 10 hours less (4). Learn more about the Analytics View. Check with team members for root causes for these differences.
|