.Keep availability up to date! v1.8.0
As a Team / Resource Manager I want to keep avaliability up to date in order to have a good base for sound planning.
(Click to enlarge) | Our first goal is to create all relevant teams and define capacity for the team members. 1: Go to Capacity Board. 2: Create new filters for all resources and specific teams. |
(Click to enlarge) | 1: Select team members for this team in the popup dialog. 2: Think of a name for this filter, e.g. 'All internal ressources' 3: Save the filter. |
(Click to enlarge) | Define capacities for permanent employees and freelancers. Create capacity entries for each team member* with the Create Capacity wizard (with extend filter option). 1: Select a ressource. Multiple Resources can be selected since version 1.5! 2: Ensure 'extend filter' option is set (If the selected ressource is not in the filter selection it will be added by this option). 3: Save the entries. Default capacities per day can be configured in the plugin configuration. |
(Click to enlarge) | Imagine the above planned team members* planned vacation or there are some public holidays. Absence time can be entered in the Absence board. 1: Go to Absence Board. 2: Create temporary absence e.g. for a leave or public holidays directly in the board. 3: Use the wizard for long term absence e.g. for a long vacation or sabbatical. |
(Click to enlarge) | Create long term absences for the team members* e.g. for a long vacation or sabbatical with the wizard. 1: Select the Resource you want to create an Absence for. Multiple Resources can be selected since version 1.5! 2: Define the respective Timeframe. 3: Enter the Absence Duration of the Resource in the defined Timeframe (- Default Value: 100% of respective Capacity). 4: Decide whether you want to add the selected Resource to the active Resource Filter to show it immediately. |
(Click to enlarge) | Use availability information in the Assignment Board for assignment planning. Go to Assignment Board. Here are some example cases: 1: Public Holiday in CW 20: Ted Cody's planning needs to be reduced by 16 hours (due to the reduced availability of 32 hours in this week). 2: Part time ressource: Tina Test works 50%, availabilty is therefore reduced 3: Long leave (e.g. vacation / sabbatical): Moe Grammer left for a long vacation, so availability is reduced to 0 for this timeframe Availability information is also relevant if you use the Create Assignment Wizard and its distribution algorithms. |
* Visibility of projects and resources depends on the following aspects:
- Restrictions in the Resource Management plugin configuration (- initially after setup there are no restrictions).
- For creation of assignments only JIRA users assigned to projects will be visible.
- For filtering of assignments only projects / resources for assignments already created will be shown.