Zum Ende des Banners springen
Zum Anfang des Banners springen

.Plan assignments with foresight! v1.9.2

Zum Ende der Metadaten springen
Zum Anfang der Metadaten

Sie zeigen eine alte Version dieser Seite an. Zeigen Sie die aktuelle Version an.

Unterschiede anzeigen Seitenhistorie anzeigen

Version 1 Aktuelle »

Plan project assignments ahead with foresight even if you don't have estimates:

(Click to enlarge)

Let's now do the planning for all relevant resources and specific teams. Go to the Assignment Board.

1: Here you can find the filter that you previously created.

2: Create filters for all resources and specific teams as learned before. Keep in mind that you need to create an assignment first to see a project or resource in the filter selection boxes.

(Warnung) Learn more about creating filters for projects and resources.


(Click to enlarge)

Define a project assignment with "Distribute value in period" strategy.

1: An example: Tina Test works 50% (20 hours per week, 4 hours each day), in CW 24 she is on vacation. We want to distribute 56 hours work for her over the next 5 weeks.

2: Select 'Create assignment'.


 

 

(Click to enlarge)

1: Select the algorithm 'Distribute value in period', the algorithm will distribute the 56 hours according to her availability in this timeframe.

(Warnung) Learn more about distribution strategy.

2: Select a project and the relevant resource (Tina Test in our example).

3: Select timeframe and the duration (next 5 weeks and 56 hours of work in our example).

4: Check availability. In our example Tina has a capacity of 100 hours (5 weeks of 20 hours). Considering her planned absence times the availability is 72 hours:

  • one week vacation (-20h)
  • already planned for strategy team 2 hours each week (-8h)

5: Save and review the result.

(Click to enlarge)

Fine tune weekly assignments for a project directly in the board. Some examples:

1: Solve conflicts: e.g. here Paul Planner's and Tina Test's plannings need to be reduced for the D&D Consulting project.

2: Postpone assignment: Ted Cody needs to start a week later with Interface development.

Check complete weekly assignments for a project (1+2).



  • Keine Stichwörter