(Click to enlarge) | The Agile Planning Popup is integrated on the JIRA Agile Board and can be accessed where you need it during sprint planning, dailies or sprint review meetings. 1: Open the popup in menu 'Agile Planning' and 'show aggregation'. 2: You can select different view modes: - Parent Issues only: Estimations of Backlog entries will be summed up (like in JIRA standard).
- Sub Tasks first: Estimations of sub tasks will be summed up, if they exist. Otherwise the estimation of the parent issues will be added. (Default)
- Sub Tasks only: Estimations of sub tasks will be summed up, if they exist. Estimations on parent issue level will be ignored at all with this method.
- Both: Estimations of the parent issue AND the subtasks are summed up.
Check out example below! 3: Aggregation mode is by task now. You can toggle between by task and by assignee. 4: Select the sprint, you would like to see. Default is the currently active sprint. |
Estimations in JIRA Agile Board (Backlog) on an user story
Estimations in JIRA Agile Board (Active sprints), sub-tasks for user story
(Click to enlarge) | Let's find out what the view mode is all about by this example for the different methods:
- Parent Issues only: Result is 1 week as just estimation of parent issue (Backlog entry) is estimated.
- Sub Tasks first: Result is 1 week 3 days as subtasks exists for this parent issue, so subtasks will be summed up and parent estimation is ignored.
- Sub Tasks only: Result is 1 week 3 days as only subtasks are summed up.
- Both: Result is 2 week 3 days as estimations of the parent issue AND the subtasks are summed up.
|
| Detect deviations from original estimates easily! If a sprint is started and the team would raise remaining estimates this is highlighted in column difference. The team can check and discuss these cases in dailies for example. |