Forecast workload / availability in order to take measures as early as possible:


(Click to enlarge)

Review assignments for your team(s) and solve conflicts as team. Go to the Assignment Board.

1:

Select Resources View2: Optional:

Create filters for all resources and specific teams as learned before. Keep in mind that you need to create an assignment first to see a project or resource in the filter selection boxes.

(Warnung) Learn more about creating filters for projects and resources.

3+

2: Select Resources View

3: Moe Grammer got under load in calendar week 18, this is indicated by a light red color

4: Identify overload

and underload

(by color): Moe Grammer has overload (red), Disy Duck has some underload (yellow) in our example.

5: The assignments for Charly, Disy and Tina will end in calendar week 28 

6: Robert is in the assignment list, but has no underlying capacity

Switch to Resources > Projects Image Added view.




(Click to enlarge)

Use the information to discuss overload e.g. with Co-Team Leaders and Resource Managers.

1+2: In our example Ted has overload and Moe could take over some additional tasks.

Use the information to discuss available capacities for additional projects e.g. with Sales.

: Identify fragmented assignments for a team member. Moe is planned to work on 4 Projects in parallel

2: Try to concentrate assignments by project and / or by period. In our example Daisy can take over the tasks of Moe.

3: Find new tasks for underload resources like Tina under load team members like Moe as of calendar week 25 in our example.